[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138879":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138879,798,1,"单选题","(2014真题)因暴雨引发山体滑坡而实施的公路交通紧急抢修项目，其合同计价方式宜采用()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","固定总价合同",false,{"key":16,"text":17,"correct":14},"B","固定单价合同",{"key":19,"text":20,"correct":14},"C","可调单价合同",{"key":22,"text":23,"correct":24},"D","成本加酬金合同",true,"紧急抢险、救灾以及施工技术特别复杂的建设工程可以采用成本加酬金合同。题干所述正是属于紧急抢险、救灾工程，宜采用成本加酬金合同。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]