[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138869,798,1,"单选题","在招投标过程中，若招标文件某分部分项工程量清单项目特征描述与设计图纸不符，投标人报价时应按（ ）确定综合单价。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计图纸",false,{"key":16,"text":17,"correct":14},"B","预算定额",{"key":19,"text":20,"correct":14},"C","企业定额",{"key":22,"text":23,"correct":24},"D","工程量清单",true,"2012年建设工程经济真题第57题 本题主要考查了投标价的编制方法。 在招投标过程中，若出现招标文件中分部分项工程量清单项目特征描述与设计图纸不符，投标人应以分部分项工程量清单的项目特征为准，确定投标报价的综合单价；若施工中施工图纸或设计变更与工程量清单项目特征描述不一致时，发、承包双方应按实际施工的项目特征，依据合同约定重新确定综合单价。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]