[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138856":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138856,798,1,"单选题","(2014真题)根据《建设工程工程量清单计价规范》GB50500-2013，投标企业可以根据拟建工程的具体施工方案进行列项的清单是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",false,{"key":16,"text":17,"correct":18},"B","措施项目清单",true,{"key":20,"text":21,"correct":14},"C","其他项目清单",{"key":23,"text":24,"correct":14},"D","规费项目清单","《建设工程工程量清单计价规范》GB50500-2013规定：措施项目清单应根据拟建工程的实际情况列项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]