[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138842,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB505000-2013），建设工程投标报价中，不得作为竞争性费用的是（ ）。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总承包服务费",false,{"key":16,"text":17,"correct":14},"B","夜间施工增加费",{"key":19,"text":20,"correct":14},"C","分部分项工程费",{"key":22,"text":23,"correct":24},"D","规费",true,"本题考查的是工程量清单计价的方法。规费和税金应按国家或省级、行业建设主管部门的规定计算，不得作为竞争性费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]