[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138836":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138836,798,1,"单选题","根据《建设工程量清单计价规范》（GB50500--2013），适宜采用综合单价法计价的措施项目费是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","脚手架工程费",true,{"key":16,"text":17,"correct":18},"B","夜间施工增加费",false,{"key":20,"text":21,"correct":18},"C","冬雨季施工增加费",{"key":23,"text":24,"correct":18},"D","二次搬运费","本题考查的是措施项目费的计算。措施项目费的综合单价法与分部分项工程综合单价的计算方法一样，就是根据需要消耗的实物工程量与实物单价计算措施费，适用于可以计算工程量的措施项目，主要是指一些与工程实体有紧密联系的项目，如混凝土模板、脚手架、垂直运输等。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]