[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138833":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138833,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），施工企业综合单价的计算有以下工作，①确定组合定额子目并计算各子目工程量；②确定人、料、机单价；③测算人、料、机的数量；④计算清单项目的综合单价；⑤计算清单项目的管理费和利润；⑥计算清单项目的人、料、机总费用，正确的步骤是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①-③-②-⑥-⑤-④",true,{"key":16,"text":17,"correct":18},"B","②-③-①-⑤-⑥-④",false,{"key":20,"text":21,"correct":18},"C","③-①-②-⑥-⑤-④",{"key":23,"text":24,"correct":18},"D","①-③-②-④-⑥-⑤","本题考查的是措施项目清单的计算。单价的计算可以概括为以下步骤：（1）确定组合定额子目；（2）计算定额子目工程量；（3）测算人、料、机消耗量；（4）确定人、料、机单价；（5）计算清单项目的人、料、机总费用；（6）计算清单项目的管理费和利润；（7）计算清单项目的综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]