[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138832,798,1,"单选题","某土方工程，招标工程质量清单中挖土方工程数量为3000㎡。投标人依据地质资料和施工方案计算的实际挖土方量为3600㎡，挖土方的人、料、机费为65000元；人工运土的人、料、机费用为25000元，机械运土的人、料、机费用58000元。企业管理费取人、料、机总费用的14%，利润率取人、料、机总费用与管理费和的8%，不考虑其他因素，则投标人挖土方的投标综合单价为（ ）元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","60.19",false,{"key":16,"text":17,"correct":14},"B","50.62",{"key":19,"text":20,"correct":14},"C","50.16",{"key":22,"text":23,"correct":24},"D","60.74",true,"本题考查的是工程量清单计价的方法。综合单价=（人、料、机总费用+管理费+利润）\u002F清单工程量。人料机总费用=65000+25000+58000=148000元；企业管理费=148000×14%=20720元；利润=（148000+20720）×8%=13497.6元；综合单价=（148000+20720+13497.6）\u002F3000=60.74元\u002Fm3。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]