[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138831":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138831,798,1,"单选题","(2014真题)投标人经复核，认为招标人公布的招标控制价未按照《建设工程工程量清单计价规范》GB50500-2013的规定进行编制的，应在招标控制价公布后()d内向招投标监督机构和工程造价管理机构投诉。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","3","投标人经复核认为招标人公布的招标控制价未按照《建设工程工程量清单计价规范》GB50500-2013的规定进行编制的，应在招标控制价公布后5d内向招投标监督机构和工程造价管理机构投诉。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]