[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138830":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138830,798,1,"单选题","按照《建设工程工程量清单计价规范》(GB 50500--2008)规定，其他项目清单中的暂列金额和暂估价（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标人可以根据企业自身特点作适当的变更",false,{"key":16,"text":17,"correct":18},"B","由招标人按估算金额确定",true,{"key":20,"text":21,"correct":14},"C","由承包人根据招标人提出的要求，按估算的费用确定",{"key":23,"text":24,"correct":14},"D","由招标人按国家或行业建设主管部门规定标准计算确定","本题主要考查了工程量清单计价的方法。 其他项目费用由暂列金额、暂估价、计日工和总承包费用构成。 暂列金额和暂估价由招标人按估算金额确定。 计日工和总承包费用由承包人根据招标人提出的要求，按估算的费用确定。 综上所述，本题正确答案为B项。 @jin",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]