[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138824":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138824,798,2,"多选题","按《建设工程工程量清单计价规范》规定，分部分项工程量清单采用综合单价计价，包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","人工费",true,{"key":16,"text":17,"correct":18},"B","措施项目费",false,{"key":20,"text":21,"correct":14},"C","施工机械使用费",{"key":23,"text":24,"correct":14},"D","管理费",{"key":26,"text":27,"correct":18},"E","规费","ACD","本题考查的是综合单价的概念。 按《建设工程工程量清单计价规范》规定，分部分项工程量清单采用综合单价计价，综合单价=人工费+材料费+施工机械使用费+管理费+利润。 综上所述，本题的正确答案为ACD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]