[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138823,798,1,"单选题","某建筑安装工程，分部分项工程量清单计价1770万元，措施项目清单计价51.34万元，其他项目清单计价100万元，规费80万元，税金68.25万元，则其单位工程报价为（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1821.34",false,{"key":16,"text":17,"correct":14},"B","1921.34",{"key":19,"text":20,"correct":14},"C","2001.34",{"key":22,"text":23,"correct":24},"D","2069.59",true,"本题主要考查了工程量清单的计价方法。 单位工程报价是由分部分项工程报价、措施项目报价、其他项目报价、规费和税金组成，即： 单位工程报价=分部分项工程费+措施项目费+其他项目费+规费+ 税金 本题单位工程报价=1770+51.34+100+80+68.25=2069.59（万元） 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]