[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138822,798,1,"单选题","按《建设工程工程量清单计价规范》规定，工程量清单计价应采用（ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工料单价法",false,{"key":16,"text":17,"correct":18},"B","综合单价法",true,{"key":20,"text":21,"correct":14},"C","扩大单价法",{"key":23,"text":24,"correct":14},"D","预算单价法","2004年建设工程经济真题第51题 本题考查的是工程量清单计价的方法。 《建设工程工程量清单计价规范》规定，分部分项工程量清单应采用综合单价计价。利用综合单价法计价，需分项计算清单项目，再汇总得到工程总造价。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]