[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138820":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138820,798,1,"单选题","工程量清单计价模式下，分部分项工程量的确定方法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按施工图图示尺寸加允许误差计算工程量",false,{"key":16,"text":17,"correct":14},"B","按施工方案计算工程总量",{"key":19,"text":20,"correct":14},"C","按施工方案加允许误差计算工程量",{"key":22,"text":23,"correct":24},"D","按施工图图示尺寸计算工程净量",true,"2009年建设工程经济真题第40题 本题主要考查了工程量清单计价的方法。 招标文件中的工程量清单标明的工程量是招标人编制招标控制价和投标人投标报价的共同基础，分部分项工程量是工程量清单编制人按施工图图示尺寸和清单工程量计算规则计算得到的工程净量。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]