[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138818,798,1,"单选题","其他项目清单中的暂列金额和暂估价由（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标人可以根据企业自身特点作适当的变更",false,{"key":16,"text":17,"correct":18},"B","招标人按估算金额确定",true,{"key":20,"text":21,"correct":14},"C","承包人根据招标人提出的要求，按估算的费用确定",{"key":23,"text":24,"correct":14},"D","招标人按国家或行业建设主管部门规定标准计算确定","本题考查其他项目费计算的内容。 其他项目费由暂列金额、暂估价、记日工、总承包服务费等内容构成。. 暂列金额和暂估价由招标人按估算金额确定。招标人在工程量清单中提供的暂估价的材料和专业工程，若属于依法必须招标的，由承包人和招标人共同通过招标确定材料单价与专业工程分包价；若材料不属于依法必须招标的，经发、承包双方协商确认单价后计价；若专业工程不属于依法必须招标的，由发包人、总承包人与分包人按有关计价依据进行计价。 综上所述，本题正确答案为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]