[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138810":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138810,798,1,"单选题","采用工程量清单计价法，分部分项工程量清单中项目的工程量是以完成后的净值计算的，对于由施工方案引起的工程费用的增加折算计入（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程索赔款",false,{"key":16,"text":17,"correct":18},"B","综合单价",true,{"key":20,"text":21,"correct":14},"C","零星工作费",{"key":23,"text":24,"correct":14},"D","预留金","本题考查的是综合单价的概念。 分部分项工程量清单中所列工程量应按附录中规定的工程量计算规则计算。工程量计算规则是指对清单项目工程量的计算规定。除另有说明外，所有清单项目的工程量以实体工程量为准， 并以完成后的净值来计算。因此，在计算综合单价时应考虑施工中的各种损耗和需要增加的工程量。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]