[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138799":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138799,798,2,"多选题","工程量清单是（ ）的依据。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进行工程索赔",true,{"key":16,"text":17,"correct":18},"B","编制项目投资估算",false,{"key":20,"text":21,"correct":14},"C","编制招标控制价",{"key":23,"text":24,"correct":14},"D","支付工程进度款",{"key":26,"text":27,"correct":14},"E","办理竣工结算","ACDE","2010年建设工程经济真题第73题 本题主要考查了工程量清单的作用。 工程量清单是工程量清单计价的基础，贯穿于建设工程的招投标阶段和施工阶段，是编制招标控制价、投标报价、计算工程量、支付工程款、调整合同价款、办理竣工结算以及工程索赔等的依据。 综上所述，本题正确答案为ACDE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]