[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138797":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138797,798,1,"单选题","新版《建设工程工程量清单计价规范》GB50500-2008包括规范条文和附录两部分，规范条文中不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程量清单编制",false,{"key":16,"text":17,"correct":14},"B","工程量清单计价",{"key":19,"text":20,"correct":14},"C","工程量清单计价表格",{"key":22,"text":23,"correct":24},"D","工程量清单项目及计算规则",true,"本题考查的是工程量清单计价规范的概念。 新版《建设工程工程量清单计价规范》GB50500-2008包括规范条文和附录两部分，规范条文共5章：总则、术语、工程量清单编制、工程量清单计价、工程量清单计价表格。 本题为选非题，综上所述，本题的正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]