[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138795,798,1,"单选题","分部分项工程量清单中所列工程量应按规定的工程量计算规则计算，该规定是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","《计价规范》附录",true,{"key":16,"text":17,"correct":18},"B","《计价规范》规范条文",false,{"key":20,"text":21,"correct":18},"C","行业协会",{"key":23,"text":24,"correct":18},"D","政府主管部门","本题考查的是工程量清单的概念。 新版《建设工程工程量清单计价规范》GB50500-2008包括规范条文和附录两部分，规范条文共5章：总则、术语、工程量清单编制、工程量请假计价、工程量清单计价表格。附录共有6个，是编制工程量清单的依据。 综上所述，本题的正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]