[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138781":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138781,798,1,"单选题","根据《建设工程工程量清单计价规范》 （GB 50500-2013），不能列入其他项目清单的是（ ）。 2016",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","专业工程暂估价",false,{"key":16,"text":17,"correct":14},"B","计日工",{"key":19,"text":20,"correct":14},"C","总承包服务费",{"key":22,"text":23,"correct":24},"D","总承包人自行分包管理费",true,"本题考查的是其他项目清单的编制。其他项目清单应根据拟建工程的具体情况，参照《建设工程工程量清单计价规范》（GB50500—2013）提供的下列4项内容列项：暂列金额、暂估价（包括材料暂估单价、工程设备暂估价、专业工程暂估价）、计日工、总承包服务费。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]