[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138772":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138772,798,2,"多选题","(2014真题)根据《建设工程工程量清单计价规范》GB50500-2013，工程量清单计价计算公式正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","措施项目费=∑措施项目工程量*措施项目综合单价",false,{"key":16,"text":17,"correct":18},"B","分部分项工程费=∑分部分项工程量*分部分项工程综合单价",true,{"key":20,"text":21,"correct":18},"C","单项工程造价=∑单位工程造价",{"key":23,"text":24,"correct":14},"D","单位工程造价=∑分部分项工程费",{"key":26,"text":27,"correct":14},"E","建设项目总造价=∑单项工程造价+工程建设其他费用+建设期利息","BC","分部分项工程费=∑分部分项工程量*分部分项工程综合单价；措施项目费=∑单价措施项目工程量*单价措施项目综合单价+∑总价措施项目费；单位工程造价=分部分项工程费+措施项目费+其他项目费+规费+税金；单项工程造价=∑单位工程造价；建设项目总造价=∑单项工程造价。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]