[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138771":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138771,798,2,"多选题","按《建设工程工程量清单计价规范》规定，分部分项工程量清单应按统一的（） 进行编制。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目编码",true,{"key":16,"text":17,"correct":14},"B","项目名称",{"key":19,"text":20,"correct":21},"C","项目特征",false,{"key":23,"text":24,"correct":14},"D","计量单位",{"key":26,"text":27,"correct":21},"E","工程量计算规则","ABD","本题的考点是分部分项工程量清单的编制。分部分项工程量清单应根据《计价规范》附录中规定的项目编码、项目名称、项目特征、计量单位、工程量计算规则进行编制。不同的分部分项工程的项目特征有所区别，并不统一，且工程量计算规则也根据具体分部分项工程的项目来规定。综上所述，本题的正确答案为ABD。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]