[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138770":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138770,798,1,"单选题","编制工程量清单时，若有总承包服务费，则应列在（ ）中。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程清单",false,{"key":16,"text":17,"correct":14},"B","措施项目清单",{"key":19,"text":20,"correct":21},"C","其他项目清单",true,{"key":23,"text":24,"correct":14},"D","规费项目清单","2007年建设工程经济真题第33题 本题主要考查了其他项目清单的编制。 其他项目清单应根据拟建工程具体情况，参照《计价规范》提供的下列4项内容列项：暂列金额、暂估价、计日工和总承包服务费。 综上所述，本题正确答案为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]