[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138766":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138766,798,2,"多选题","按照《建设工程工程量清单计价规范》规定，工程量清单应当由分部分项工程量清单及（ ）组成。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","项目编码",false,{"key":16,"text":17,"correct":18},"B","措施项目清单",true,{"key":20,"text":21,"correct":18},"C","其他项目清单",{"key":23,"text":24,"correct":18},"D","规费项目清单",{"key":26,"text":27,"correct":18},"E","税金项目清单","BCDE","本题主要考查了工程量清单编制的方法。 工程量清单由分部分项工程量清单、措施项目清单、其他项目清单、规费项目清单和税金项目清单组成。 综上所述，本题正确答案为BCDE项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]