[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138764":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138764,798,1,"单选题","根据《建设工程工程量清单计价规范》，十二位分部分项工程量清单项目编码中，由工程量清单编制人设置的是第（ ）位。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","三至四",false,{"key":16,"text":17,"correct":14},"B","五至六",{"key":19,"text":20,"correct":14},"C","七至九",{"key":22,"text":23,"correct":24},"D","十至十二",true,"2007年建设工程经济真题第34题 本题主要考查了分部分项工程量清单的编制。 分部分项工程量清单项目编码以五级编码设置，采用十二位阿拉伯数字表示。一至九位应按《计价规范》附录的规定统一设置，十至十二位应根据拟建工程的工程量项目清单名称设置（即由工程量清单编制人设置）。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]