[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138762":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138762,798,2,"多选题","根据拟建工程的具体情况，列入工程量清单中其他项目清单的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","暂列金额",true,{"key":16,"text":17,"correct":18},"B","已完工程及设备保护费",false,{"key":20,"text":21,"correct":14},"C","暂估价",{"key":23,"text":24,"correct":14},"D","计日工",{"key":26,"text":27,"correct":18},"E","文明施工费","ACD","2007年建设工程经济真题第78题 本题主要考查了其他项目清单的编制。 其他项目清单应根据拟建工程具体情况，参照《计价规范》提供的下列4项内容列项：暂列金额、暂估价、计日工和总承包服务费。 综上所述，本题正确答案为ACD项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]