[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138758":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138758,798,2,"多选题","工程量清单由（ ）等组成。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",true,{"key":16,"text":17,"correct":18},"B","综合单价分析清单",false,{"key":20,"text":21,"correct":14},"C","措施项目清单",{"key":23,"text":24,"correct":18},"D","其他项目价格清单",{"key":26,"text":27,"correct":18},"E","主要材料价格清单","AC","2006年建设工程经济真题第78题 本题的考查点为工程量清单的组成。 工程量清单主要由分部分项工程量清单、措施项目清单和其他项目清单组成。 故本题正确答案为A、C。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]