[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138755":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138755,798,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），招标工程量清单的准确性和完整性应由（ ）负责。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投标人",false,{"key":16,"text":17,"correct":14},"B","招标人指定的招标代理机构",{"key":19,"text":20,"correct":14},"C","招标人的上级部门",{"key":22,"text":23,"correct":24},"D","招标人",true,"2013年建设工程经济真题第32题 本题考查的是工程量清单编制的概念。 采用工程量清单方式招标，工程量清单必须作为招标文件的组成部分，由招标人提供，并对其准确性和完整性负责。一经中标签订合同，工程量清单即为合同的组成部分。工程量清单应由具有编制能力的招标人或受其委托具有相应资质的工程造价咨询人进行编制。 综上所述，本题的正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]