[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138753":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138753,798,1,"单选题","分部分项工程清单不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目金额",true,{"key":16,"text":17,"correct":18},"B","项目编码",false,{"key":20,"text":21,"correct":18},"C","计量单位",{"key":23,"text":24,"correct":18},"D","工程数量","本题主要考查了分部分项工程量清单的编制。 分部分项工程量淸单应包括项目编码、项目名称、项目特征、计量单位和工程量五个部分，应根据《计价规范》附录中规定的项目编码、项目名称、项目特征、计量单位和工程量计算规则进行编制，因此，分部分项工程量清单中不包括项目金额。 本题为选非题，综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]