[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138750":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138750,798,1,"单选题","暂估价是招标人在工程量清单中提供的用于支付必然发生但暂时不能确定价格的材料的单价以及专业工程的金额，应列入（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",false,{"key":16,"text":17,"correct":14},"B","措施项目费用",{"key":19,"text":20,"correct":21},"C","其他项目清单",true,{"key":23,"text":24,"correct":14},"D","规费项目清单","本题主要考查了其他项目清单的编制。 其他项目清单是指分部分项工程量清单、措施项目清单所包含的内容以外，因招标人的特殊要求而发生的与拟建工程有关的其他费用项目和相应数量清单。其他项目清单应根据拟建工程的具体情况，参照《计价规范》提供的下列4项内容列项，包括暂列金额、暂估价、计日工、总承包服务费。因此，暂估价应计入其他项目清单。 综上所述，本题正确答案为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]