[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138749":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138749,798,1,"单选题","根据《建筑工程工程量清单计价规范》（GB50500--2008），分部分项工程量清单中，确定综合单价的依据是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计量单位",false,{"key":16,"text":17,"correct":18},"B","项目特征",true,{"key":20,"text":21,"correct":14},"C","项目编码",{"key":23,"text":24,"correct":14},"D","项目名称","2011年建设工程经济真题第33题 本题主要考查了分部分项工程量清单的编制。 分部分项工程量清单的项目特征是确定一个清单项目综合单价的重要依据，在编制的工程量清单中必须对其项目特征进行准确和全面的描述。 综上所述，本题正确答案为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]