[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138746":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138746,798,1,"单选题","根据《建设工程工程量清算单计价规范》（GB50500—2008），施工招标投标时，工程量清单应由（ ）负责提供。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程招标代理机构",false,{"key":16,"text":17,"correct":14},"B","工程设计单位",{"key":19,"text":20,"correct":14},"C","招投标管理部门",{"key":22,"text":23,"correct":24},"D","招标人",true,"2012年建设工程经济真题第54题 本题主要考查了工程量清单的编制方法。 采用工程量清单方式招标，工程量清单必须作为招标文件的组成部分，由招标人提供，并对其准确性和完整性负责。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]