[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138743":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138743,798,1,"单选题","施工图预算编制的传统计价模式和工程量清单计价模式的主要区别在于（ ）不同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计算方式和管理方式",true,{"key":16,"text":17,"correct":18},"B","费用构成",false,{"key":20,"text":21,"correct":18},"C","编制主体",{"key":23,"text":24,"correct":18},"D","作用","本题主要考查了施工图预算编制的模式。 按照预算造价的计算方式和管理方式的不同，施工图预算可以划分为两种不同的计价模式，即传统计价模式和工程量清单计价模式。 综上所述，本题正确答案为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]