[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138736,798,1,"单选题","当拟建工程与已完工程的建设条件和工程设计相同时，用已完工程的预算审查拟建工程的同类工程预算的方法是（ ）。 2016",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","标准预算审查法",false,{"key":16,"text":17,"correct":14},"B","分组审查法",{"key":19,"text":20,"correct":14},"C","重点审查法",{"key":22,"text":23,"correct":24},"D","对比审查法",true,"本题考查的是施工图预算审查的方法。对比审查法是当工程条件相同时，用已完工程的预算或未完但已经过审查修正的工程预算对比审查拟建工程的同类工程预算的一种方法。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]