[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138729,798,1,"单选题","在进行施工图预算审查时，利用计算出的底层建筑面积或楼（地）面面积，对楼面找平层、顶棚抹灰等的工程量进行审查。这种审查方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","逐项审查法",false,{"key":16,"text":17,"correct":18},"B","分组计算审查法",true,{"key":20,"text":21,"correct":14},"C","对比审查法",{"key":23,"text":24,"correct":14},"D","“筛选”审查法","本题主要考查了施工图预算的审查方法。 施工图预算的审查方法有全面审查法、标准预算审查分组计算审查法、对比审查法、筛选审查法、重点审查法和分解对比审查法等。其中分组审查法就是把预算中有关项目按类别划分若干组，利用同组中的一组数据审查分项工程量，如一般的建筑工程中将底层建筑面积编为一组，先计算底层建筑面积或楼（地）面面积，从而得知楼面找平层、顶棚抹灰的工程量等。 综上所述，本题正确答案为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]