[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138715":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138715,798,1,"单选题","(2014真题)采用工程量清单招标时，提供招标工程量清单并对其完整性和准确性负责的单位是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发布招标文件的招标人",true,{"key":16,"text":17,"correct":18},"B","发放招标文件的招标代理人",false,{"key":20,"text":21,"correct":18},"C","编制清单的工程造价咨询人",{"key":23,"text":24,"correct":18},"D","招标人的上级管理单位","招标工程量清单必须作为招标文件的组成部分，由招标人提供，并对其准确性和完整性负责。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]