[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138687":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138687,798,1,"单选题","（2019年真题）某建设项目的建筑面积为10000㎡，按类似工程概算指标计算的一般土建工程单位概算造价为1158.84元\u002F㎡（其中人、料、机费用为800元\u002F㎡），项目所在地建筑安装工程管理费率为8%，按人、料、机和企业管理费计算的规费费率为15%，利润率为7%;增值税税率为9%，与类似工程概算指标规定的结构特比较，该项目结构有部分变更，换出结构构件中每100㎡的人、料、机费用为12450元，换入结构构件中每100㎡的人、料、机费用为15800元，人、料、机费用均不包含增值税可抵扣进项模额，则该项目一般土建工程修正后的概算单价为(（2019年真题）（2019年真题）)元\u002F㎡。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","833.50",false,{"key":16,"text":17,"correct":18},"B","1207.36",true,{"key":20,"text":21,"correct":14},"C","1192.34",{"key":23,"text":24,"correct":14},"D","1316.84","P207-215 结构变化修正概算指标(元\u002F㎡ ) =原概算指标+换入结构的工程量x换入结构的人科机费用单价+换出结构的工程最x换出结构的人料机费用单价; 则调整后的概算单价= ( 800+15800\u002F100-12450\u002F100)x (1+8%)x (1+15%) x (1+7%)x (1+9%) =1207.36 (元\u002F㎡)。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]