[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138686":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138686,798,2,"多选题","建设项目总概算书的内容有编制说明和（ ）。( 2015真题 )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单位工程概算表",true,{"key":16,"text":17,"correct":18},"B","分部分项工程概算表",false,{"key":20,"text":21,"correct":14},"C","单项工程综合概算表",{"key":23,"text":24,"correct":14},"D","工程建设其他费用概算表",{"key":26,"text":27,"correct":14},"E","总概算表","ACDE","本题考查的是建设工程项目总概算的编制方法。总概算书的内容：（1）封面、签署页及目录；（2）编制说明；（3）总概算表；（4）工程建设其他费用概算表；（5）单项工程综合概算表；（6）单位工程概算表；（7）附录：补充估价表。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]