[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138678":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138678,798,1,"单选题","(2014真题)编制设备安装工程概算，当初步设计的设备清单不完备，可供采用的安装预算单价及扩大综合单价不全时，适宜采用的概算编制方法是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","概算定额法",false,{"key":16,"text":17,"correct":14},"B","扩大单价法",{"key":19,"text":20,"correct":14},"C","类似工程预算法",{"key":22,"text":23,"correct":24},"D","概算指标法",true,"当初步设计的设备清单不完备，或安装预算单价及扩大综合单价不全，无法采用预算单价法和扩大单价法时，可采用概算指标编制概算。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]