[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138656":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138656,798,1,"单选题","根据现行规定，在审查概算的投资规模、生产能力等是否符合原批准的可行性研究报告或者立项批文时，若发现概算总投资超过原批准投资估算的（ ）以上，需要进一步审查超估算的原因。( 2015真题 )",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":18},"B","10%",true,{"key":20,"text":21,"correct":14},"C","3%",{"key":23,"text":24,"correct":14},"D","8%","本题考查的是设计概算审查的内容。审查概算的投资规模、生产能力、设计标准、建设用地、建筑面积、主要设备、配套工程、设计定员等是否符合原批准可行性研究报告或立项批文的标准。如概算总投资超过原批准投资估算10%以上，应进一步审查超估算的原因。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]