[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138648":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1138648,798,2,"多选题","企业应当组织工程、技术、财会等部门的相关专业人员对编制的概预算重审查（ ）等是否真实、完整、准确。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","编制依据",true,{"key":16,"text":17,"correct":14},"B","定额套用",{"key":19,"text":20,"correct":21},"C","单价的计算方法",false,{"key":23,"text":24,"correct":14},"D","项目内容",{"key":26,"text":27,"correct":14},"E","工程量的计算","ABDE","2005年建设工程经济真题第71题 本题考查的设计概算的审查内容。 设计概算审查首先要进行设计概算的编制依据的审查。其次要对单位工程设计概算进行审查，其中包括建筑工程概算的审查和设备及安装工程概算的审查。建筑工程概算的审查主要内容有工程量审查、采用的定额或指标的审查、材料预算价格的审查、各项费用的审查等。设备及安装工程概算审查的重点是设备清单与安装费用的计算。 综上所述，本题的正确答案为ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程经济","建筑工程",0]