[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138643,798,1,"单选题","在对综合概算和总概算进行审查时，如概算总投资超过原批准投资估算达到一定比例，需要进一步审查超估值的原因，这个比例是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10%以上",true,{"key":16,"text":17,"correct":18},"B","5%以上",false,{"key":20,"text":21,"correct":18},"C","15%",{"key":23,"text":24,"correct":18},"D","20%","本题主要考查设计概算的审查内容。 在综合概算和总概算的审查中，当审查概算的投资规模、生产能力、设计标准、建设用地、建筑面积、主要设备、 配套工程、设计定员等是否符合原批准可行性研究报告或立项批文的标准时，如概算总投资超过原批准投资估算10%以上，应进一步审查超估算的原因。 综上所述，本题A项正确。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]