[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138641,798,1,"单选题","在进行单位建筑工程设计概算构成审查时，对材料预算价格的审查，重点是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料原价",false,{"key":16,"text":17,"correct":14},"B","运输费用",{"key":19,"text":20,"correct":21},"C","耗用量最大的主要材料",true,{"key":23,"text":24,"correct":14},"D","是否有重复计算或遗漏","本题主要考查了设计概算审查的内容。 材料预算价格的审查以耗用量最大的主要材料作为审查的重点，同时着重审查材料原价、运输费用以及节约材料运输费用的措施。 综上所述，本题正确答案为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]