[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138618,798,1,"单选题","某拟建项目的建筑安装工程费为1100万元，设备及工（器）具购置费为600万元，工程建设其他费为300万元，则该项目涨价预备费的计算基数为（）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1400",false,{"key":16,"text":17,"correct":14},"B","1700",{"key":19,"text":20,"correct":14},"C","1300",{"key":22,"text":23,"correct":24},"D","2000",true,"本题考核的是涨价预备费的计算基数。涨价预备费以建筑安装工程费、设备及工器具购置费之和为计算基数。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]