[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138616,798,1,"单选题","某建设工程项目建筑安装工程费为2000万元，设备及工器具购置费为800万元，工程建设其他费为300万元，基本预备费率为8%，该项目的基本预备费为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","248",true,{"key":16,"text":17,"correct":18},"B","160",false,{"key":20,"text":21,"correct":18},"C","184",{"key":23,"text":24,"correct":18},"D","224","本题考查的是基本预备费。根据基本预备费计算公式，基本预备费=（设备及工器具购置费+建筑安装工程费+工程建设其他费用）×基本预备费费率=（2000+800+300）×8%=248（万元），因此选项A正确。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]