[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1138609,798,1,"单选题","涨价预备费是以（ ）为计算基数的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设备工器具购置费、建筑安装工程费和工程建设其他费之和",false,{"key":16,"text":17,"correct":14},"B","基本预备费",{"key":19,"text":20,"correct":14},"C","投资总额",{"key":22,"text":23,"correct":24},"D","建筑安装工程费、设备工器具购置费之和",true,"本题主要考查了预备费的组成。 涨价预备费是指建设工程项目在建设期内由于价格等变化引起投资增加，需要事先预留的费用，涨价预备费以建筑安装工程费、设备及工器具购置费之和为计算基数。 综上所述，本题正确答案为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]