[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138608":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1138608,798,1,"单选题","某建设项目实施到第2年时，由于规范变化导致某分项目工程量增加，因此增加的费用应从建设投资中的（ ）支出。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基本预备费",true,{"key":16,"text":17,"correct":18},"B","涨价预备费",false,{"key":20,"text":21,"correct":18},"C","建设期利息",{"key":23,"text":24,"correct":18},"D","工程建设其他费用","2013年建设工程经济真题第50题 本题考查的是基本预备费的概念。 基本预备费是指在项目实施中可能发生难以预料的支出，需要预先预留的费用，又称不可预见费。主要指设计变更及施工过程中可能增加工程量的费用。 综上所述，本题的正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]