[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138605":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138605,798,1,"单选题","某建设项目期初估算的建筑安装工程费和设备工器具购置费为1500万元，建设期为2年，第2年计划完成估算投资的40%，建设期内年平均价格上涨率为3%，则第2年的涨价预备费为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","18.00",false,{"key":16,"text":17,"correct":18},"B","36.54",true,{"key":20,"text":21,"correct":14},"C","63.54",{"key":23,"text":24,"correct":14},"D","636.54","本题主要考查了涨价预备费的计算。 涨价预备费是以建筑工程安装费、设备及工器具购置费之和为计算基数。 因此，本题正确答案为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]