[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138603,798,1,"单选题","某建设工程项目在建设初期估算的建筑安装工程费1 000万元、设备及工器具购置费为4 000万元，工程其他费为300万元，基本预备费率为10％，则该项目的基本预备费估算是 （ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","500",false,{"key":16,"text":17,"correct":18},"B","530",true,{"key":20,"text":21,"correct":14},"C","430",{"key":23,"text":24,"correct":14},"D","130","本题主要考查了基本预备费。 基本预备费是指在项目实施中可能发生难以预料的支出，需要预先预留的费用，又称不可预见费。 基本预备费=（设备及工器具购置费+建筑安装工程费+工程建设其他费）×基本预备费率 本题中基本预备费=（4000+1000+300）×10%=530（万元） 因此，本题正确答案为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]