[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1138601,798,1,"单选题","（2019年真题）某建设项目的程费用为1500万元，工程建设其他费用为200万元，场地准备和临时设施费用的5%计算，预计项目完工后拆除工程产生的清理费用为20万元，拆除工程可收回材料作价5万元。则该项目的场地准备和临时设施费为(（2019年真题）)万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","70",false,{"key":16,"text":17,"correct":18},"B","90",true,{"key":20,"text":21,"correct":14},"C","75",{"key":23,"text":24,"correct":14},"D","100","P177-182 新建项目的场地准备和临时设施费应根据实际工程量估算，或按工程费用的比例计算。改扩建项目一般只计拆除清理费发生拆除清理费时可按新建同类工程造价或主材费、设备费的比例计算。凡可回收材料的拆除工程采用以料抵工方式冲抵拆除清理费。场地准备和临时设施费=工程费用×费率+拆除清理费，故1500*5%+20-5=90万元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]