[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1138596":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1138596,798,1,"单选题","编制某企业改扩建项目的投资估算时，生产准备费的计算基数应为（ ）。 2016",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","新增建筑安装工程费用",false,{"key":16,"text":17,"correct":14},"B","原有设计定员",{"key":19,"text":20,"correct":21},"C","新增设计定员",true,{"key":23,"text":24,"correct":14},"D","全部设计定员","本题考查的的是与未来企业生产经营有关的其他费用。生产准备费是指新建项目或新增生产能力的项目，为保证竣工交付使用进行必要的生产准备所发生的费用。新建项目按设计定员为基数计算，改扩建项目按新增设计定员为基数计算。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程经济","建筑工程",0]